JHGS – Construction Update #18 December 2014

Project Update And Schedule, Aerial Pictures From Time Lapse Camera, South Portal Entrance, North Portal Entrance, Truck Traffic Update, Campbellton Off-Site Project Office, Brewster Lake Road and Trail Closures, Economic Opportunities, Environment, City of Campbell River Council Tour, John Hart Project Donation to the SPCA, John Hart Project Interpretive Centre, People Profile – Nathalie Dinnissen, […]

READ MORE

JHGS – Construction Update #17 November 2014

Project Update And Schedule, Construction Pictures, Brewster Lake Road Bridge, Truck Traffic Update, Campbellton Off-Site Project Office – Traffic, Blasting and Trail Closures, Environment, People Profile – Clayton Macdonald, Construction – Point of Interest – John Hart project wins the gold award for project financing Download the report: JHGSRPConstRptNov2014

READ MORE

JHGS-Construction Update #16 October 2014

Project Update And Schedule Construction Pictures – Aerial Pictures From Time Lapse Camera Construction Pictures Around the South Portal Entrance Construction Pictures Around the North Portal Entrance Rock Drilling Brewster Lake Road Bridge Environment – Tree Compensation Environment – Water Management Economic – Business Events in October Local Business Profile – T-Mar Industries People Profile […]

READ MORE

JHGS – Construction Update #15 September 2014

John Hart Generating Station Replacement Project September 2014 Community Construction Update Report #15 Download the document: JHGSRPConstRptSept2014

READ MORE

JHGS – Construction Update #14 August 2014

Project status update for August 2014. South portal entrance, Temporary bridge over penstocks, Station View Trail, Interpretive centre and economic opportunities. Download the report: JHGSRPConstRpt-August2014

READ MORE

JHGS – Construction Update #13 July 2014

Project Status Update, Minister Bill Bennett Event, Noise and Site Blasting, City of Campbell River – Water Infrastructure and Station View Trail all addressed Download the report: JHGSRPConstRpt-July2014

READ MORE

JHGS – Construction Update #12 June 2014

Approximate Project Schedule, The Two Underground Portals, Construction Work Has Begun, Temporary Project Site Office Has Been Selected, Station View Trail, Economic Opportunities, People Profile – Amber Ashenhurst, Construction – Point of Interest Download the document: JHGSRPConstRpt-June2014

READ MORE

JHGS – Construction Update #11 – May 2014

InPower BC is anticipating the John Hart site release from BC Hydro in June to allow them to start the project work. Work on the various plans and permits continues. The site work may commence in late June. Download the document: JHGSRPConstRptMay2014

READ MORE

JHGS – Construction Update #10 – March-April 2014

InPower BC is in the process of completing plans and designs to provide them with a “leave to commence” from the Comptroller of Water Rights and a “site release” from BC Hydro in order to begin construction. Generally, SNC-Lavalin plans to begin the site clearing near the tunnel entrances in July, and in October begin […]

READ MORE

JHGS – Construction Update #09 – February 2014

On February 28, BC Hydro issued a news release on the contract award signing with InPower BC, a special purpose project company in which SNC-Lavalin Group Inc. ultimately has 100% interest, for the John Hart Generating Station Replacement Project. This provides the green light for them to mobilize workers to the site. Download the document: […]

READ MORE