Dec 31, 2014
JHGS – Construction Update #18 December 2014
Project Update And Schedule, Aerial Pictures From Time Lapse Camera, South Portal Entrance, North Portal Entrance, Truck Traffic Update, Campbellton Off-Site Project Office, Brewster Lake Road and Trail Closures, Economic Opportunities, Environment, City of Campbell River Council Tour, John Hart Project Donation to the SPCA, John Hart Project Interpretive Centre, People Profile – Nathalie Dinnissen, […]
READ MORENov 28, 2014
JHGS – Construction Update #17 November 2014
Project Update And Schedule, Construction Pictures, Brewster Lake Road Bridge, Truck Traffic Update, Campbellton Off-Site Project Office – Traffic, Blasting and Trail Closures, Environment, People Profile – Clayton Macdonald, Construction – Point of Interest – John Hart project wins the gold award for project financing Download the report: JHGSRPConstRptNov2014
READ MOREOct 30, 2014
JHGS-Construction Update #16 October 2014
Project Update And Schedule Construction Pictures – Aerial Pictures From Time Lapse Camera Construction Pictures Around the South Portal Entrance Construction Pictures Around the North Portal Entrance Rock Drilling Brewster Lake Road Bridge Environment – Tree Compensation Environment – Water Management Economic – Business Events in October Local Business Profile – T-Mar Industries People Profile […]
READ MORESep 28, 2014
JHGS – Construction Update #15 September 2014
John Hart Generating Station Replacement Project September 2014 Community Construction Update Report #15 Download the document: JHGSRPConstRptSept2014
READ MOREAug 29, 2014
JHGS – Construction Update #14 August 2014
Project status update for August 2014. South portal entrance, Temporary bridge over penstocks, Station View Trail, Interpretive centre and economic opportunities. Download the report: JHGSRPConstRpt-August2014
READ MOREJul 28, 2014
JHGS – Construction Update #13 July 2014
Project Status Update, Minister Bill Bennett Event, Noise and Site Blasting, City of Campbell River – Water Infrastructure and Station View Trail all addressed Download the report: JHGSRPConstRpt-July2014
READ MOREJun 28, 2014
JHGS – Construction Update #12 June 2014
Approximate Project Schedule, The Two Underground Portals, Construction Work Has Begun, Temporary Project Site Office Has Been Selected, Station View Trail, Economic Opportunities, People Profile – Amber Ashenhurst, Construction – Point of Interest Download the document: JHGSRPConstRpt-June2014
READ MOREMay 30, 2014
JHGS – Construction Update #11 – May 2014
InPower BC is anticipating the John Hart site release from BC Hydro in June to allow them to start the project work. Work on the various plans and permits continues. The site work may commence in late June. Download the document: JHGSRPConstRptMay2014
READ MOREApr 27, 2014
JHGS – Construction Update #10 – March-April 2014
InPower BC is in the process of completing plans and designs to provide them with a “leave to commence” from the Comptroller of Water Rights and a “site release” from BC Hydro in order to begin construction. Generally, SNC-Lavalin plans to begin the site clearing near the tunnel entrances in July, and in October begin […]
READ MOREFeb 28, 2014
JHGS – Construction Update #09 – February 2014
On February 28, BC Hydro issued a news release on the contract award signing with InPower BC, a special purpose project company in which SNC-Lavalin Group Inc. ultimately has 100% interest, for the John Hart Generating Station Replacement Project. This provides the green light for them to mobilize workers to the site. Download the document: […]