Ladore Spillway Seismic Upgrade Project
Project Timeline
2015
Project Initiation
Scoping, engineering, First Nation consultation and community engagement
2022
Design
Completion of preliminary design
2023
BCUC Review
Initiation and completion of BC Utilities Commission regulatory review
2023
Begin Procurement
Initiate procurement process via BC Bid
2024
Funding
BC Hydro project funding approval
2024
Contract Award
Award procurement contract
2025
Construction
Construction begins
About The Project
Project objectives:
- Replace the three spillway gates and related works, such as the hoist system, so they can retain and pass water in a controlled manner downstream post-earthquake.
- Install new equipment and upgrades to the existing protection and control equipment to meet current reliability standards, including improved post-earthquake operation.
Project Video
Watch the latest project video below or at this link on Vimeo
Latest News
Feb 03, 2025
Ladore Dam upgrades underway for seismic safety in Campbell River to cost up to $379M
The Ladore Dam near Campbell River is undergoing seismic upgrades to reduce the risk of damage in the event of a major earthquake or flood. Built in 1949 with the powerhouse completed in 1957, the Ladore Dam is one of three hydroelectric dams on the Campbell River system seeing safety upgrades. The John Hart Dam […]
See All News UpdatesSee All News
- BC Hydro contractor update for Campbell River seismic upgrade projects
- BC Hydro contractor update for Campbell River seismic upgrade projects
- More major BC Hydro projects underway near Campbell River with $2.7 billion total spend
- Upgrades to B.C. Hydro dams near Campbell River could cost up to $1.7B
- BC Hydro submits Ladore and Strathcona projects to BC Utilities Commission