John Hart Dam Seismic Upgrade Project

Project Timeline

2014
Project Initiation
Scoping, engineering, First Nation consultation and community engagement
2020
Design
Completion of preliminary design
2021
BCUC Review
Initiation of BC Utilities Commission regulatory review
2021
Begin Procurement
Initiate procurement process via BC Bid
2023
Funding
BC Hydro project funding approval
2023
Contract Award
Award procurement contract for civil works
2023
Construction
Construction begins
2026
Contract Award
Award contract for spillway gates
2030
Completion
Construction completed