Ladore Spillway Seismic Upgrade Project
Project Timeline
2015
Project Initiation
Scoping, engineering, First Nation consultation and community engagement
2022
Design
Completion of preliminary design
2023
BCUC Review
Initiation and completion of BC Utilities Commission regulatory review
2023
Begin Procurement
Initiate procurement process via BC Bid
2024
Funding
BC Hydro project funding approval
2024
Contract Award
Award procurement contract
2025
Construction
Construction begins
About The Project
Project objectives:
- Replace the three spillway gates and related works, such as the hoist system, so they can retain and pass water in a controlled manner downstream post-earthquake.
- Install new equipment and upgrades to the existing protection and control equipment to meet current reliability standards, including improved post-earthquake operation.
Project Video
Watch the latest project video below or at this link on Vimeo
Latest News
Aug 10, 2023
Upgrades to B.C. Hydro dams near Campbell River could cost up to $1.7B
Proposed seismic upgrades to the Strathcona and Ladore dams on the Campbell River hydroelectric system, along with an already approved project to strengthen the John Hart dam, could cost a total of $1.17 billion to $1.74 billion, according to B.C. Hydro estimates.
See All News UpdatesSee All News
- BC Hydro submits Ladore and Strathcona projects to BC Utilities Commission
- B.C. Hydro seeking contractor for major work on Ladore Dam
- Dam upgrade on popular Campbell River lake won’t affect recreation
- Bidding set to open for seismic work on Island dams
- Campbell River Chamber Website Collaboration With BC Hydro Will Connect Workers To Three New Projects
Browse and search our full archive of news for all projects
See All News Updates